Open Space Infrastructure Australia   Timber Design & Construction
Home About Us Boardwalks Footbridges Buildings Other Projects Contact Us
 
BoardWalks

  Erskin Falls
  Rosebud Boardwalk
  Frankston Boardwalk Stage 2
  Sweetwater Creek
  Sheoak Boardwalk
  Benalla Boardwalk
  Frankston Boardwalk Stage 1
  Gulls Way Staircase
  Cape Bridgewater Platform
  Point Addis Staircases
  Olivers Hill Staircase - Frankston
  Yanggai Barring Ringwood
  Lake Elizabeth General Works
  Seaford Boardwalk and Platform
  Red Rock Staircase and Platform
  Benalla Boardwalk Stage 2
  Anglesea Patform
  Rippleside Boardwalk
  Freeway Project - Donvale
  Drysdale Steps
  Aireys Inlet
  Triplet Falls
  Tim Neville Reserve
  Broken Falls - Grampians
  Breamlea Steps
  Eastlink
  Frankston Stage 3
  Bells Beach Steps
  The Dell - Clifton Springs
  Buckleys Stairs
  Casey Boardwalk and Bridge
  Lake Jubilee Fishing Platforms
  Clayton Retarding Basin



Point Addis Staircases
Construction of two separate staircases in difficult terrain

Kane on the job 
Kane on the job
Client: N.R.E.

Date: 1 December 2001

Duration: 8 weeks

Cost: under $80,000.00

  Construction Underway in difficult coastal terrain

  Construction nearing completion

  Second set of Steps to beach

  Second set of Steps

Located near Bells Beach outside of Torquay. Stairs are a total of over 70 metres in length, replaced existing dilapidated structures. Stairs lead to remote interesting beaches.